Technical and economic study of striking and clearing operations in buildings under construction.: Case study in Bogotá, Colombia



Document title: Technical and economic study of striking and clearing operations in buildings under construction.: Case study in Bogotá, Colombia
Journal: Dyna (Medellín)
Database:
System number: 000537755
ISSN: 0012-7353
Authors: 1
1
1
3
Institutions: 1Pontificia Universidad Javeriana, Facultad de Ingeniería Civil, Bogotá. Colombia
2
3Universitat Politècnica de València, ICITECH, Valencia. España
Year:
Season: Dic
Volumen: 83
Number: 199
Pages: 102-107
Country: Colombia
Language: Inglés
Spanish abstract El presente artículo evalúa el beneficio económico de la aplicación del Nuevo Procedimiento Simplificado (NPS), reflejado en los plazos de construcción en edificaciones de entrepisos sucesivos. El edificio de referencia corresponde a un edificio residencial resuelto con pórticos y entrepisos en una dirección, de concreto reforzado ubicado en la ciudad de Bogotá. Las fases desarrolladas en cumplimiento del objetivo planteado, constaron de una caracterización de los componentes, el estudio de distintas alternativas para determinar la transmisión de cargas entre entrepisos y puntales, y una revisión de los precios de alquiler de equipo auxiliar y personal del edificio de referencia. Aplicando dicho procedimiento se realizó una evaluación económica de los plazos obtenidos en cada una de las operaciones estudiadas. Se destaca que el análisis del proceso constructivo de la estructura de la edificación empleando el NPS permite lograr ahorros considerables en la ejecución de la edificación sin poner en riesgo la integridad de la estructura.
English abstract This paper evaluates the economic benefits of shorter construction times that can be attained by applying the New Simplified Procedure (NSP) in multi-storey buildings. The reference building was a multi-storey residential reinforced concrete framework structure with one-way slabs located in Bogotá, Colombia. The study was divided into different phases including the characterization of the components, a study of the different methods to determine load transmissions between slabs and shores, and a review of the cost of renting shoring and formwork materials and labor costs for the building under study. After applying the procedure, an economic assessment was carried out on the execution times obtained in each of the operations studied. The analysis of the construction process of the building structure using the NSP showed that considerable savings can be achieved in construction times without any risk for the integrity of the structure.
Keyword: Nuevo Procedimiento Simplificado,
Puntales,
Estimación de tiempos,
Estimación de cargas,
Estimación costos personal y equipo
Keyword: New Simplified Procedure,
Shores,
Time estimations,
Load estimations,
Estimation of personnel and equipment costs
Full text: Texto completo (Ver HTML) Texto completo (Ver PDF)